NCS Technologies, Inc., B-403435, November 8, 2010

  • By GCPC GovCon Legal Team
  • December 9, 2010
  • Terms of the Solicitation

Link: GAO Opinion

Agency: Department of Homeland Security

Disposition: Protest sustained.

Keywords: Protesting the Terms of a Solicitation

General Counsel P.C. Highlight: An agency may include requirements that restrict competition in a solicitation only to the extent they are necessary to satisfy its legitimate needs.

—————————————————————————————————————————–

NCS Technologies, Inc. (NCS) protests the terms of a request for quotations (RFQ), issued by the Department of Homeland Security (DHS), for computer hardware.

The RFQ was issued to DHS’s First Source contract holders and several small vendors on the General Services Administration’s (GSA) Federal Supply Schedule (FSS) 70, provided for establishing a blanket purchase agreement with a five-year term for commercial off-the-shelf laptops, desktops, and monitors. Among the requirements identified for the computers and monitors was that all of the computers and monitors must be from the same manufacturer and must use an Intel-based microprocessor. Vendors were also informed that they must submit with their quotations, “a 3rd party review less than 2 years old such as that provided by ‘Square Trade, PC Magazine, Byte, etc.’ demonstrating that the proposed manufacturer suite of equipment has been rated average or above in reliability as show in the report provided.”

NCS objects to the requirement that all computers and monitors be from the same manufacturer and that the computers use an Intel-based microprocessor. NCS also objects to the third party review requirement.

GAO states that although a contracting agency has the discretion to determine its needs and the best method to accommodate them, the agency may include restrictive requirements only to the extent they are necessary to satisfy its legitimate needs. GAO reviews challenges to allegedly restrictive requirements to determine whether the restrictions are reasonably necessary to meet the agency’s needs. The adequacy of the agency’s justification is ascertained through examining whether the agency’s explanation is reasonable, that is, whether the explanation can withstand logical scrutiny.

GAO’s review of the record finds that there is no analysis or documentation supporting the agency’s justification for its standardization requirement. The agency has provided a statement from an information technology project manager, who generally asserts that standardizing the computers and monitors to a single manufacturer reduces costs and provides other benefits. However, the project manager does not identify any analyses or studies to support this; nor does the project manager provide any explanation or analyses that would show the extent to which these claimed benefits would be achieved by this restriction. GAO is unable to find that the agency’s asserted justification for the restriction is reasonable and therefore finds that the agency should review this requirement. The agency has also not provided any analyses or studies supporting its claimed need for Intel-based microprocessors.

Finally, GAO finds that the agency should also reconsider its requirement for third party reviews since the phrase “average or above in reliability” is unclear to the meaning of both “average or above” and “reliability,” as the meaning of these words vary depending upon the reviewer. The protest is sustained and GAO recommends that the agency review its requirements for a single manufacturer and Intel-based microprocessors to determine whether these reflect the agency’s legitimate needs.

Share

Related Posts

Agency Arguing the Futile in Pre-Award Bid Protest

November 17, 2022

Matter of BAE Systems Norfolk Ship Repair, Inc.

January 4, 2022

In the Matter of: CR/ZWS LLC

November 3, 2017

Qwest Government Services, Inc. dba CenturyLink QGS, B-407835, March 7, 2013

April 3, 2013

Comments are closed

Search Bid Protest Weekly

Need help with a bid protest?

Call us at: 703-556-0411 Or fill out this form:

Categories

  • 8(a) Sole Source Awards
  • Acknowledging Amendments
  • Adequately Written Proposal
  • Adverse Agency Action
  • Adverse Impact Analysis
  • Agency Tender
  • Alternate or Previously-Approved Product
  • Alternative Dispute Resolution
  • Ambiguity in Solicitation
  • Attorney's Fees
  • Bad Faith in Evaluation
  • Below-Cost Offer
  • Best Value
  • Beyond the Scope
  • Bias
  • Bid and Proposal Costs
  • Bid Bond
  • Bid Compliance
  • Bid Protest Decisions
  • Bid Protest Jurisdiction
  • Bid Protests
  • Bidding Best Practices
  • Blanket Purchase Agreement
  • Blanket Purchase Order
  • Blog Articles
  • Bona Fide Needs Rule
  • Brand Name or Equal
  • Broad Agency Announcement
  • Brooks Act
  • Bundling or Consolidation
  • Buy American Act
  • Cancellation of a Solicitation
  • Capability of Contractor
  • CCR Registration
  • Certificate of Competency (COC)
  • Certification Requirements
  • Changes Clause
  • Clarifications
  • Clear and Convincing Evidence
  • Clearly Meritorious Protest
  • Clerical Error
  • Commercial Item Acquisition
  • Competitive Range
  • Compliance
  • Conflict of Interest
  • Construction Design-Build
  • Construction Services
  • Contract Administration
  • Contract Modifications
  • Contracting Preference
  • Contractor Responsibility
  • Corporate Capability
  • Corrective Action
  • Cost Accounting System
  • Cost Evaluation
  • Cost Realism
  • Cost Reimbursement Contract
  • Cost-Technical Trade-Off
  • Customary Commercial Practice
  • CVE
  • DCAA Audit
  • Debriefing
  • Default Termination
  • Deficient Price Proposal
  • Delivery Order jurisdiction
  • Delivery Schedule
  • Designated Employee Agent
  • Disclosure of Price
  • Disclosure of Source Selection-Sensitive Information
  • Discussions
  • Disqualification
  • Documentation of Evaluation
  • Domestic Production Requirement
  • Education Center Articles
  • Electronic Filing
  • Evaluation Criteria
  • Evaluations
  • Events
  • Executive Order Compliance
  • Experience of Contractor
  • Experience Requirement
  • Facility Clearance
  • Fair Market Price
  • FASA
  • FedBizOpps
  • Federal Prison Industries (FPI)
  • Filing Deadlines
  • Final Evaluation
  • Final Proposal Revisions
  • Financial Responsibility
  • Fixed Price Contract
  • Former Government Employees
  • FSS Contract
  • GAO Bid Protest Review
  • GAO Jurisdiction
  • GAO Standard of Review
  • Government Contracts
  • Government Office Closings
  • Government Surplus Material
  • GSA Lease
  • HUBZone
  • ID/IQ
  • Impaired Objectivity
  • In-Sourcing
  • Incentive Fee
  • Inclement Weather Delay
  • Incomplete Proposal
  • Incorporation by Reference
  • Incumbent Capture
  • Incumbent Status
  • Independent Government Estimate (IGE)
  • Individual Environmental Report
  • Industrial Mobilization
  • Innovations
  • Interested Party
  • Invitation for Bid
  • Invited Contractor
  • Javits-Wagner-O'Day Act
  • Joint Venture
  • Key Personnel
  • Labor Hours
  • Labor Rate Pricing
  • Late Proposals
  • Late Submissions
  • Level of Effort
  • Licensing Requirements
  • Limitation on Subcontracting
  • Liquidated Damages
  • Lost Proposal
  • Lowest Price Technically Acceptable
  • Mail-Box Rule
  • Management Planning
  • Market Research
  • MAS Contracts
  • Material Misrepresentation
  • Material Solicitation Amendment
  • Material Solicitation Terms
  • Meaningful Discussions
  • Micro-Purchase Threshold
  • Minimum Requirements
  • Misleading Discussions
  • Mistake
  • Mitigation Strategy
  • Multiple Awards
  • NAICS Code
  • National Security
  • Negotiation
  • News
  • Non-Procurement Instruments
  • Novations
  • Offeror Representations
  • OMB Circular A-76
  • Option Exercise
  • Oral Presentations
  • Organizational Conflict of Interest (OCI)
  • Page Limitations
  • Past Performance
  • Past Performance Information Retrieval System (PPIRS)
  • Performance Based Standards
  • Permits and Responsibilities
  • Personal Conflicts of Interest
  • Post-Award Changes to the Contract
  • Post-Protest Re-Evaluations
  • Practicable Alternative
  • Pre-Award Protest
  • Pre-award vs. Post-award Requirements
  • Pre-Qualification of Offerors
  • Pre-Solicitation Notice
  • Prejudice
  • Price Calculation Error
  • Price Calculation Error
  • Price Evaluation
  • Price of FSS Task Order Quote
  • Price Realism
  • Price Reasonableness
  • Price Reduction
  • Procurement Announcement
  • Procurement Integrity
  • Product Testing
  • Proposal Acceptance Period
  • Proposal Detail
  • Proposal Evaluation
  • Proposal Extension
  • Proposal Standards
  • Proposals
  • Protest Terms of Solicitation
  • Protester Comments
  • Public-Private Competition
  • Randolph-Sheppard Act (RSA)
  • Rate Tenders
  • Re-Certification of Size Status
  • Reconsideration
  • Reevaluation
  • Reevaluation Standards
  • Reimbursed Attorney's Fees
  • Reimbursement of Protest Costs
  • Rejection of Proposal
  • Relaxation or Waiver of Requirement
  • Relevancy of Past Performance
  • Reliance on the Proposal
  • Remedies
  • Requirements Contract
  • Responsibility
  • Responsiveness
  • Restricted Competition
  • Resumes
  • Revision of Proposal
  • Revision of Proposals
  • Risk
  • Rule of Two
  • SBA Status protest
  • Scope of GAO Review
  • SDVOSB Set-Asides
  • Significant Issue Exception
  • Simplified Acquisition Procedures
  • Site Visit
  • Size Determination
  • Size Protest
  • Small Business Innovation Research (SBIR) Program
  • Small Business Set-Asides
  • Small Business Subcontracting Goals
  • Sole-Source Award
  • Solicitation Amendment
  • Solicitation Requirements
  • Source Approval
  • Source Selection Authority
  • Source Selection Decision
  • Source Selection Plan
  • Sources Sought Notice
  • Staffing Plan
  • State and Local Requirements
  • Status of Forces Agreement (SOFA)
  • Subcontract Protest
  • Subcontractor Experience
  • Suspension and Debarment
  • Taking Exception to RFP Requirements
  • Task Orders
  • Teaming Agreement
  • Technical Acceptability
  • Technical Evaluation
  • Technical Evaluation
  • Termination of Award
  • Terms of the Solicitation
  • Timeliness of Protest
  • Timely Filing
  • Timely Performance
  • Timely Proposal Submission
  • Trade Agreement Act
  • Unbalanced Pricing
  • Unduly Restrictive Terms
  • Unequal Access to Information
  • Unequal Treatment of Offerors
  • Uniform Time Act of 1996
  • Unstated Evaluation Criteria
  • Unusual and Compelling Urgency
  • Use of Appropriated Funds
  • Veterans First
  • VIP Database
  • VOSB Set Asides
  • Wage Determination

Get Help


Talk to an
attorney who
specializes
in bid protests:

+1-703-556-0411
Email

Keep up to date
on bid protest
decisions and
policies:

© 2023 Bid Protest Weekly

  • LinkedIn
  • Google +
  • Twitter
  • Facebook
  • Home
  • Bid Protest Ed Center
  • Blog
  • Topics
  • About Us
  • Contact Us
  • Home
  • Bid Protest Ed Center
    • WHAT is a bid protest?
    • WHO can file a bid protest
    • DO I need an Attorney?
    • WHY Should you file a bid protest?
    • WHEN Must you file a bid protest?
    • WHERE can you file a bid protest?
    • READING the RFP
  • Blog
  • Topics
  • About Us
  • Contact Us
  • LinkedIn
  • Google +
  • Twitter
  • Facebook

+1-703-556-0411