Globecomm Systems, Inc., B-405303.2; B-405303.3, October 31, 2011

  • By GCPC GovCon Legal Team
  • December 19, 2011
  • Competitive RangeSource Selection Plan

Link: GAO Opinion

Agency: General Services Administration

Disposition: Protest denied.

Keywords: Competitive range; source selection plan

General Counsel P.C. Highlight: A poorly written protest that fails to properly argue the facts and law will not be sustained where the record indicates the agency’s action were reasonable.

—————————————————————————————————————————–

GAO denies the protest of Globecomm Systems, Inc. where its proposal was eliminated from the competitive range by the General Services Administration (GSA) under a request for proposals (RFP), issued by GSA for worldwide commercial satellite communications (COMSATCOM) end-to-end solutions.

Globecomm specifically asserts that its proposal fully met the evaluation criteria and should have received ratings that were higher than unacceptable under both the technical/management evaluation factor and the corporate experience evaluation factor. GAO states that it will review an agency’s evaluation and exclusion of a proposal from the competitive range for reasonableness and consistency with the solicitation criteria and applicable statutes and regulations. Contracting agencies are not required to retain proposals in the competitive range that are not among the most highly rated or that the agency otherwise reasonably concludes have no realistic prospect of being selected for award. Further, the evaluation of proposals is a matter within the discretion of the contracting agency, since the agency is responsible for defining its needs and the best method of accommodating them. In reviewing an agency’s evaluation, GAO will not reevaluate proposals, but instead will examine the agency’s evaluation to ensure that it was reasonable and consistent with the solicitation’s stated evaluation criteria and with procurement statutes and regulations. Finally, it is the offeror’s responsibility to submit a well-written proposal, with adequately detailed information to demonstrate compliance with the solicitation requirements, and an offeror’s mere disagreement with the agency’s judgment concerning the adequacy of the proposal is not sufficient to establish that the agency acted unreasonably.

First, based on GAO’s review of the record, GAO finds nothing unreasonable in the agency’s determination that Globecomm’s proposal failed to demonstrate an adequate understanding of the importance of the RFP’s requirement regarding timely delivery where the proposal failed to provide a detailed delivery schedule and simply asserted that Globecomm was committed to timely delivery. Although the protester maintains that, even if the solicitation reasonably contemplated more detailed scheduling information, the proposal’s deficiency in this regard should not be considered a significant weakness, it fails to meaningfully dispute or otherwise show to be unreasonable the agency’s analysis of the specific weaknesses in its proposal regarding the delivery requirement; accordingly, Globecomm’s assertions constitute mere disagreement with the agency’s judgment. On the record here, GAO does not question the agency’s determination that Globecomm’s proposal failed to meaningfully comply with the solicitation’s scheduling and delivery requirements.

Next, nothing in Globecomm’s protest nor its comments refute, and in most instances fail to even address why Globecomm believes the agency’s evaluation of its corporate experience was unreasonable. In pursuing this protest, Globecomm has copied portions of its proposal, yet provided virtually no supporting explanation as to why the various copied portions of its proposal render the agency’s criticisms invalid. Based on the record presented, GAO again finds no basis to question the agency’s evaluation of Globecomm’s proposal as unacceptable with regard to the corporate experience factor.

Globecomm also contends that the agency improperly used a predetermined cutoff score to establish the competitive range based on whether or not an offeror has one or more significant weaknesses for the technical/management evaluation factor. The record fails to support the protester’s argument in this regard. The record shows that all eight of the offerors eliminated from the competitive range were rated unacceptable under both the technical/management factor and the corporate experience factor. The record does not indicate that there was a predetermined cutoff based on the number of weaknesses for the technical/management evaluation factor.

Similarly, the protester asserts that the agency failed to consider all of the evaluation factors in making the competitive range decision. However, the record shows that the competitive range consisted of other offerors. Globecomm and seven other offerors were eliminated based on their ratings of unacceptable for both the technical/management and corporate experience evaluation factors. The record indicates that the agency conducted a detailed evaluation of all offerors under all evaluation factors, including price, to make the competitive range determination. On this record, Globecomm’s assertion that the agency failed to consider all of the evaluation factors is without merit.

Finally, Globecomm argues that the agency failed to comply with the source selection plan when determining the competitive range. An agency’s source selection plan is an internal guide that does not give rights to parties; it is the RFP’s evaluation scheme, not internal agency documents such as source selection plans, to which an agency is required to adhere in evaluating proposals. The protest is denied.

Share

Related Posts

Matter of Science Applications International Corporation

February 28, 2022

Competitive Range – Matter of: Pinnacle Solutions, Inc.

August 25, 2017

Global Technology Systems, Inc., B-408461, August 30, 2013

September 10, 2013

KAES Enterprises, LLC, B-407964.4, August 21, 2013

September 3, 2013

Comments are closed

Search Bid Protest Weekly

Need help with a bid protest?

Call us at: 703-556-0411 Or fill out this form:

Categories

  • 8(a) Sole Source Awards
  • Acknowledging Amendments
  • Adequately Written Proposal
  • Adverse Agency Action
  • Adverse Impact Analysis
  • Agency Tender
  • Alternate or Previously-Approved Product
  • Alternative Dispute Resolution
  • Ambiguity in Solicitation
  • Attorney's Fees
  • Bad Faith in Evaluation
  • Below-Cost Offer
  • Best Value
  • Beyond the Scope
  • Bias
  • Bid and Proposal Costs
  • Bid Bond
  • Bid Compliance
  • Bid Protest Decisions
  • Bid Protest Jurisdiction
  • Bid Protests
  • Bidding Best Practices
  • Blanket Purchase Agreement
  • Blanket Purchase Order
  • Blog Articles
  • Bona Fide Needs Rule
  • Brand Name or Equal
  • Broad Agency Announcement
  • Brooks Act
  • Bundling or Consolidation
  • Buy American Act
  • Cancellation of a Solicitation
  • Capability of Contractor
  • CCR Registration
  • Certificate of Competency (COC)
  • Certification Requirements
  • Changes Clause
  • Clarifications
  • Clear and Convincing Evidence
  • Clearly Meritorious Protest
  • Clerical Error
  • Commercial Item Acquisition
  • Competitive Range
  • Compliance
  • Conflict of Interest
  • Construction Design-Build
  • Construction Services
  • Contract Administration
  • Contract Modifications
  • Contracting Preference
  • Contractor Responsibility
  • Corporate Capability
  • Corrective Action
  • Cost Accounting System
  • Cost Evaluation
  • Cost Realism
  • Cost Reimbursement Contract
  • Cost-Technical Trade-Off
  • Customary Commercial Practice
  • CVE
  • DCAA Audit
  • Debriefing
  • Default Termination
  • Deficient Price Proposal
  • Delivery Order jurisdiction
  • Delivery Schedule
  • Designated Employee Agent
  • Disclosure of Price
  • Disclosure of Source Selection-Sensitive Information
  • Discussions
  • Disqualification
  • Documentation of Evaluation
  • Domestic Production Requirement
  • Education Center Articles
  • Electronic Filing
  • Evaluation Criteria
  • Evaluations
  • Events
  • Executive Order Compliance
  • Experience of Contractor
  • Experience Requirement
  • Facility Clearance
  • Fair Market Price
  • FASA
  • FedBizOpps
  • Federal Prison Industries (FPI)
  • Filing Deadlines
  • Final Evaluation
  • Final Proposal Revisions
  • Financial Responsibility
  • Fixed Price Contract
  • Former Government Employees
  • FSS Contract
  • GAO Bid Protest Review
  • GAO Jurisdiction
  • GAO Standard of Review
  • Government Contracts
  • Government Office Closings
  • Government Surplus Material
  • GSA Lease
  • HUBZone
  • ID/IQ
  • Impaired Objectivity
  • In-Sourcing
  • Incentive Fee
  • Inclement Weather Delay
  • Incomplete Proposal
  • Incorporation by Reference
  • Incumbent Capture
  • Incumbent Status
  • Independent Government Estimate (IGE)
  • Individual Environmental Report
  • Industrial Mobilization
  • Innovations
  • Interested Party
  • Invitation for Bid
  • Invited Contractor
  • Javits-Wagner-O'Day Act
  • Joint Venture
  • Key Personnel
  • Labor Hours
  • Labor Rate Pricing
  • Late Proposals
  • Late Submissions
  • Level of Effort
  • Licensing Requirements
  • Limitation on Subcontracting
  • Liquidated Damages
  • Lost Proposal
  • Lowest Price Technically Acceptable
  • Mail-Box Rule
  • Management Planning
  • Market Research
  • MAS Contracts
  • Material Misrepresentation
  • Material Solicitation Amendment
  • Material Solicitation Terms
  • Meaningful Discussions
  • Micro-Purchase Threshold
  • Minimum Requirements
  • Misleading Discussions
  • Mistake
  • Mitigation Strategy
  • Multiple Awards
  • NAICS Code
  • National Security
  • Negotiation
  • News
  • Non-Procurement Instruments
  • Novations
  • Offeror Representations
  • OMB Circular A-76
  • Option Exercise
  • Oral Presentations
  • Organizational Conflict of Interest (OCI)
  • Page Limitations
  • Past Performance
  • Past Performance Information Retrieval System (PPIRS)
  • Performance Based Standards
  • Permits and Responsibilities
  • Personal Conflicts of Interest
  • Post-Award Changes to the Contract
  • Post-Protest Re-Evaluations
  • Practicable Alternative
  • Pre-Award Protest
  • Pre-award vs. Post-award Requirements
  • Pre-Qualification of Offerors
  • Pre-Solicitation Notice
  • Prejudice
  • Price Calculation Error
  • Price Calculation Error
  • Price Evaluation
  • Price of FSS Task Order Quote
  • Price Realism
  • Price Reasonableness
  • Price Reduction
  • Procurement Announcement
  • Procurement Integrity
  • Product Testing
  • Proposal Acceptance Period
  • Proposal Detail
  • Proposal Evaluation
  • Proposal Extension
  • Proposal Standards
  • Proposals
  • Protest Terms of Solicitation
  • Protester Comments
  • Public-Private Competition
  • Randolph-Sheppard Act (RSA)
  • Rate Tenders
  • Re-Certification of Size Status
  • Reconsideration
  • Reevaluation
  • Reevaluation Standards
  • Reimbursed Attorney's Fees
  • Reimbursement of Protest Costs
  • Rejection of Proposal
  • Relaxation or Waiver of Requirement
  • Relevancy of Past Performance
  • Reliance on the Proposal
  • Remedies
  • Requirements Contract
  • Responsibility
  • Responsiveness
  • Restricted Competition
  • Resumes
  • Revision of Proposal
  • Revision of Proposals
  • Risk
  • Rule of Two
  • SBA Status protest
  • Scope of GAO Review
  • SDVOSB Set-Asides
  • Significant Issue Exception
  • Simplified Acquisition Procedures
  • Site Visit
  • Size Determination
  • Size Protest
  • Small Business Innovation Research (SBIR) Program
  • Small Business Set-Asides
  • Small Business Subcontracting Goals
  • Sole-Source Award
  • Solicitation Amendment
  • Solicitation Requirements
  • Source Approval
  • Source Selection Authority
  • Source Selection Decision
  • Source Selection Plan
  • Sources Sought Notice
  • Staffing Plan
  • State and Local Requirements
  • Status of Forces Agreement (SOFA)
  • Subcontract Protest
  • Subcontractor Experience
  • Suspension and Debarment
  • Taking Exception to RFP Requirements
  • Task Orders
  • Teaming Agreement
  • Technical Acceptability
  • Technical Evaluation
  • Technical Evaluation
  • Termination of Award
  • Terms of the Solicitation
  • Timeliness of Protest
  • Timely Filing
  • Timely Performance
  • Timely Proposal Submission
  • Trade Agreement Act
  • Unbalanced Pricing
  • Unduly Restrictive Terms
  • Unequal Access to Information
  • Unequal Treatment of Offerors
  • Uniform Time Act of 1996
  • Unstated Evaluation Criteria
  • Unusual and Compelling Urgency
  • Use of Appropriated Funds
  • Veterans First
  • VIP Database
  • VOSB Set Asides
  • Wage Determination

Get Help


Talk to an
attorney who
specializes
in bid protests:

+1-703-556-0411
Email

Keep up to date
on bid protest
decisions and
policies:

© 2023 Bid Protest Weekly

  • LinkedIn
  • Google +
  • Twitter
  • Facebook
  • Home
  • Bid Protest Ed Center
  • Blog
  • Topics
  • About Us
  • Contact Us
  • Home
  • Bid Protest Ed Center
    • WHAT is a bid protest?
    • WHO can file a bid protest
    • DO I need an Attorney?
    • WHY Should you file a bid protest?
    • WHEN Must you file a bid protest?
    • WHERE can you file a bid protest?
    • READING the RFP
  • Blog
  • Topics
  • About Us
  • Contact Us
  • LinkedIn
  • Google +
  • Twitter
  • Facebook

+1-703-556-0411