Link: GAO Opinion
Agency: Financial Crimes Enforcement Network
Disposition:
__________________________________________________________________________________________________________________
GAO Digest:
A nonseverable services contract that is not separated for performance by fiscal year may not be funded on an incremental basis without statutory authority. Failure to obligate the estimated cost (or ceiling) of a nonseverable cost-reimbursement contract at the time of award violated the bona fide needs rule.
Contract modifications to a cost-reimbursement contract increasing original ceiling are chargeable to appropriations available when the modifications were approved by the contracting officer. The actual date the agency records the obligation in its books is irrelevant to the determination of when the obligation arises and what fiscal year appropriation to charge.
A provision in an annual appropriations act designating that a portion of a lump-sum amount “shall be available for” a specific project does not preclude the use of other available appropriations for the project.
General Counsel P.C. Highlight:
The Office of Inspector General, Department of the Treasury (OIG), has requested a decision regarding the Financial Crimes Enforcement Network’s (FinCEN) obligation, expenditure, and accounting of appropriated funds for its Bank Secrecy Act Direct Retrieval and Sharing System (BSA Direct) project. OIG states that FinCEN obligated about $17.7 million on the project during fiscal years 2004 through 2006, and questions FinCEN’s use of funding in each of those three fiscal years, including whether FinCEN violated the Antideficiency Act.
At issue here is the application of the bona fide needs rule to the BSA Direct contract, both on June 30, 2004, when FinCEN entered into the contract and, later, when FinCEN modified the contract. The bona fide needs rule was developed by the accounting officers of the United States to implement one of the oldest fiscal statutes, now codified at 31 U.S.C. sect. 1502(a), which provides that “an appropriation or fund limited for obligation to a definite period is available only for payment of expenses properly incurred during the period of availability or to complete contracts properly made within that period of availability.” As this statute has been interpreted and applied, an appropriation is available only to fulfill a genuine or bona fide need of the time period of availability of the appropriation. On June 30, 2004, FinCEN entered into a cost-reimbursement contract, agreeing to pay EDS for the costs it incurred in the design, development and deployment of the BSA Direct system plus a negotiated fee. In determining what appropriation to charge for a service contract such as FinCEN’s BSA Direct contract, it is important to distinguish between a nonseverable services contract and a severable services contract.
The general rule is that a nonseverable service is considered a bona fide need at the time the agency orders the service and, therefore, should be charged to an appropriation current at the time the agency enters into the contract. A nonseverable service is one that requires the contractor to complete and deliver a specified end product (for example, a final report of research). Severable services, which are recurring in nature, are bona fide needs at the time the service is completed, and obligations for severable services should be charged to appropriations current at that time. A severable service is a recurring service or one that is measured in terms of hours or level of effort rather than work objectives. Whether a contract is for severable or nonseverable services affects how the agency may fund the contract; severable services contracts may be incrementally funded, while nonseverable services contracts must be fully funded at the time of the award of the contract.
The FinCEN contract at issue called for delivery of a defined end product (the design, development, and deployment of a data retrieval system), and as the contract was written, the work could not feasibly be subdivided (and, in fact, was not subdivided) for separate performance by fiscal year. The contract required the contractor to provide a data retrieval system that will “be implemented by or before 9/30/05, a timeframe that will meet FinCEN’s critical mission needs. The contract stated further that “the Contractor is expected to employ a disciplined, incremental approach to analyze, design, develop, and deploy the BSA Direct System and to provide that the developed system meets FinCEN’s technical and business requirements within a predictable schedule and budget . . .” It stipulated, “It is essential that the completed and tested system be provided as soon as possible . . .” Accordingly, as a threshold matter, GAO concludes that the contract here was a nonseverable services contract. Consequently, FinCEN should have recorded an obligation of $8,982,985.01 to its fiscal year 2004 appropriations for its estimated cost, including the fixed fee. FinCEN, however, recorded an obligation of only $2 million at the time of award in fiscal year 2004.
FinCEN’s inclusion of section B.7 (Incremental Funding), which limited the agency’s liability to $2 million at the time it awarded the contract, did not remedy the bona fide needs problem that necessarily arose when FinCEN attempted to charge its fiscal year 2004 obligation to subsequent fiscal years. Section B.7 apparently was an attempt to avoid an Antideficiency Act violation. The difficulty, however, is that FinCEN in section B.4, consistent with FAR sect. 16.301–1, established its obligation as $8.9 million. Because GAO concludes that FinCEN failed to properly charge its obligation to the correct fiscal year, GAO recommends that the agency adjust its accounts by deobligating $6,982,985.01 from its fiscal year 2005 appropriations and charging that amount to its appropriations available for fiscal year 2004. If, in doing so, FinCEN determines that the obligation exceeds the amount available in fiscal year 2004, it should report an Antideficiency Act violation.
The record shows that FinCEN, during fiscal year 2005, modified the contract a number of times to increase funding on the contract beyond the original ceiling of $8,982,985. FinCEN states that, with the exception of two modifications that it recorded against fiscal year 2006 appropriations, it charged the modifications to three separate appropriations: the fiscal year 2005 salaries and expenses appropriation, which included a provision making $7.5 million available for BSA Direct; the fiscal year 2004 salaries and expenses appropriation, of which $8,152,000 was to remain available until September 30, 2005; and the fiscal year 2003 salaries and expenses appropriation, of which $3,400,000 was to remain available until September 30, 2005.
With regard to a cost-reimbursement contract like FinCEN’s BSA Direct contract, agencies should charge modifications that increase the original ceiling to an appropriation current at the time of the modification. Modifications increasing the ceiling are discretionary in nature and therefore are considered to reflect a new need. As such, the modifications should be charged to funds available when the modification is signed by the contracting officer. For the contract modifications at issue here, the contracting officer approved increases beyond the initial $8.9 million ceiling established in the contract. Accordingly, the fiscal year 2005 modifications increasing the ceiling beyond $8,982,985 were chargeable to appropriations available for fiscal year 2005. In all but two instances, FinCEN, in fact, did charge the modifications to appropriations that were available for fiscal year 2005.
The record shows that FinCEN charged two fiscal year 2005 modifications to fiscal year 2006 appropriations, Contract Modifications Nos. 7 and 9. Both of these modifications were executed in fiscal year 2005; Modification 7 was signed by the contracting officer on September 12, 2005, and Modification 9 was signed on September 13, 2005. It appears that the agency confused the event of incurring an obligation with the act of recording the obligation. The agency points to spreadsheet entries indicating that on October 5, 2005, it recorded obligations for the BSA Direct contract against fiscal year 2006 appropriations.
The Recording Statute, 31 U.S.C. sect. 1501, requires agencies to record an obligation at the time an authorized contracting officer signs a contract modification. The fact that the actual recording of the obligation is not made at that time is immaterial insofar as determining what fiscal year appropriation to charge. While it appears that FinCEN did not record the obligations until fiscal year 2006, it incurred the obligations in fiscal year 2005 when it signed the modifications. FinCEN should have recorded the obligations against appropriations available for obligation in fiscal year 2005, not its fiscal year 2006 appropriations. Accordingly, FinCEN should adjust its accounts.
Because of the $7.5 million provision in FinCEN’s fiscal year 2005 appropriation, and the fact that FinCEN obligated more than that on the contract, OIG questions whether FinCEN violated the Antideficiency Act. FinCEN’s fiscal year 2005 salaries and expenses appropriation provided FinCEN “$72,502,000, of which $7,500,000 shall be available for BSA Direct.” FinCEN points out that while it obligated funds in fiscal year 2005 that exceeded $7.5 million, it did not obligate more than $7.5 million from its fiscal year 2005 salaries and expenses appropriation. Rather, it also obligated funds from its fiscal years 2003 and 2004 appropriations, each of which was available through fiscal year 2005.
FinCEN could legally draw on its fiscal years 2003 and 2004 appropriations, to the extent that they had sufficient unobligated balances, for costs related to the BSA Direct project. The $7.5 million provision did not preclude the agency’s use of these appropriations. GAO sees nothing in the language of the fiscal year 2005 appropriation or its legislative history to suggest that Congress intended to restrict the availability of these appropriations for the project. The plain language of the $7.5 million provision addressed only the use of the fiscal year 2005 appropriation, affirmatively directing that a portion, $7.5 million, be used for the BSA project. The language makes $7.5 million available only for the BSA Direct project. The fiscal years 2003 and 2004 appropriations contained lump sum amounts that were available for the necessary expenses of FinCEN for obligations incurred through September 30, 2005. GAO therefore concludes that use of the other appropriations to obligate funds in excess of $7.5 million did not violate the Antideficiency Act.