Onsite OHS, B-406449, May 30, 2012

Link: GAO Decision Protestor: Onsite OHS Agency: Department of Energy Disposition: Protest Denied. _____________________________________________________________________________________________________ GAO Digest: Protester’s contention that the agency improperly failed to consider its proposal is denied where the agency did not receive the proposal due to the…

Onsite OHS, B-406449, May 30, 2012 was last modified: June 20th, 2012 by General Counsel PC 703-556-0411

U.S. Aerospace, Inc., B-403464; B-403464.2, October 6, 2010

Link: GAO Opinion Agency: Department of the Air Force Disposition: Protest denied. Keywords: Timely Proposal submission General Counsel P.C. Highlight: It is an offeror’s responsibility to deliver its proposal to the proper place at the proper time; proposals that are received…

U.S. Aerospace, Inc., B-403464; B-403464.2, October 6, 2010 was last modified: October 14th, 2010 by General Counsel PC 703-556-0411

Hunter Contracting Company, B-402575, March 31, 2010

Link: GAO Opinion Agency: Department of Homeland Security, Bureau of Customs and Border Protection Disposition: Protest denied. Keywords: Timely bid submission; Inclement weather delay General Counsel P.C. Highlight: It is an offeror’s responsibility to deliver its proposal to the proper…

Hunter Contracting Company, B-402575, March 31, 2010 was last modified: April 8th, 2010 by General Counsel PC 703-556-0411

CFS-INC, JV, B-401809.2, March 31, 2010

Link: GAO Opinion Agency: General Services Administration Disposition: Protest denied. Keywords: Timely proposal submission; Government office closings General Counsel P.C. Highlight: Even though federal employees were allowed a delayed arrival and unscheduled leave, a delayed arrival time or allowance of…

CFS-INC, JV, B-401809.2, March 31, 2010 was last modified: April 8th, 2010 by General Counsel PC 703-556-0411