Verizon Wireless, B-406854, B-406854.2, September 17, 2012
Posted on October 3, 2012 | No CommentsLink: GAO Decision Protestor: Verizon Wireless Agency: General Services Administration Disposition: Protest Sustained. _____________________________________________________________________________________________________ GAO Digest: Protest challenging the terms of a solicitation is timely where the solicitation expressly permitted offerors to take exception to its terms, the agency did not advise the protester that... -
W. Gohman Construction Co., B-401877, December 2, 2009
Posted on January 12, 2010 | No CommentsLink: GAO Opinion Agency: Department of the Army Disposition: Protest denied. Keywords: Taking Exception to RFP Requirements General Counsel P.C. Highlight: An Agency may not accept a proposal that takes exception to the Agency’s stated requirements. —————————————————————————————————————————– W. Gohman Construction protested the award of a... -
Northern Light Productions, B-401182, June 1, 2009
Posted on June 1, 2009 | No CommentsLink: GAO Opinion Agency: Department of the Interior Disposition: Protest denied. _________________________________________________________________________________________________________________ GAO Digest: Protest that an agency’s inclusion of data rights requirements in the solicitation’s evaluation scheme precluded an agency determination that the protester’s proposal was unacceptable on the basis that it took exception...