To reimburse? or NOT to reimburse? (That’s the Protest)

To reimburse? or NOT to reimburse? (That’s the Protest)

OUTCOME:  Agency did not unduly delay corrective action when it changed the evaluation criteria in question prior to the deadline for submitting its agency report to GAO.   As a result, GAO deemed the action by the agency to be sufficiently…

To reimburse? or NOT to reimburse? (That’s the Protest) was last modified: January 12th, 2015 by Rocky Galloway

Eagle Support Services Corporation, B-405077.7, B-405077.8, September 17, 2012

Link: GAO Decision Protestor: Eagle Support Services Corporation Agency: Department of the Army Disposition: Protest Denied. _____________________________________________________________________________________________________ GAO Digest: Protest of an agency’s technical evaluation and selection decision is denied where the evaluation and source selection were reasonable and consistent…

Eagle Support Services Corporation, B-405077.7, B-405077.8, September 17, 2012 was last modified: October 17th, 2012 by General Counsel PC 703-556-0411

Phacil, Inc., B-406628, July 5, 2012

Link: GAO Decision Protestor: Phacil, Inc. Agency: Department of Agriculture Disposition: Protest Denied. _____________________________________________________________________________________________________ GAO Digest: Protest challenging an agency’s evaluation of quotations and selection decision is denied where the record shows that the agency’s evaluation and issuance of a…

Phacil, Inc., B-406628, July 5, 2012 was last modified: August 8th, 2012 by General Counsel PC 703-556-0411