Corrective Action Archive
-
Naval Systems, Inc., B-407090.3, November 20, 2012
Posted on December 5, 2012 | No CommentsLink: GAO Decision Protestor: Naval Systems, Inc. Agency: Department of the Navy Disposition: Protest Denied. _____________________________________________________________________________________________________ GAO Digest: Protest challenging agency’s proposed corrective action in response to an earlier protest is denied where the record shows that the agency’s corrective action– revising the solicitation, obtaining... -
EOD Technology, Inc., B-406978.2, B-406978.3, August 20, 2012
Posted on August 29, 2012 | No CommentsLink: GAO Decision Protestor: EOD Technology, Inc. Agency: Department of the Army Disposition: Protest Dismissed. _____________________________________________________________________________________________________ General Counsel PC Highlight: EOD Technology, Inc. protested the corrective action taken by the agency under an RFP for security services in Afghanistan. The RFP provided for award to... -
URS Federal Services, Inc. – Costs, B-406140.4, July 17, 2012
Posted on August 15, 2012 | No CommentsLink: GAO Decision Protestor: URS Federal Services, Inc. Agency: Internal Revenue Service Disposition: Request Granted in Part, Denied in Part. _____________________________________________________________________________________________________ GAO Digest: GAO will recommend that agency reimburse protester for the costs of filing and pursuing its protest, where the agency did not take... -
Kingdomware Technologies – Costs, B-406228.2, May 10, 2012
Posted on May 16, 2012 | No CommentsLink: GAO Decision Protestor: Kingdomware Technologies Inc. Agency: Department of Veterans Affairs Disposition: Request Denied. _____________________________________________________________________________________________________ GAO Digest: Protester is not entitled to reimbursement of protest costs after agency took corrective action where protest was not clearly meritorious. General Counsel PC Highlight: Kingdomware Technologies Inc.... -
Data and Analytic Solutions, Inc., B-405278.2, February 27, 2012
Posted on March 14, 2012 | No CommentsLink: GAO Decision Protestor: Data and Analytic Solutions, Inc. Agency: Department of Health and Human Services Disposition: Protest Denied. ____________________________________________________________________________________________________ GAO Digest: In a negotiated procurement for the award of a cost reimbursement contract where offerors were provided a range of estimated monthly workloads and... -
Jones Lang LaSalle Americas, Inc., B-406019.2, February 14, 2012
Posted on March 14, 2012 | No CommentsLink: GAO Decision Protestor: Jones Lang LaSalle Americas, Inc. Agency: Department of the Army Disposition: Protest Denied. ____________________________________________________________________________________________________ GAO Digest: Protest objecting to proposed corrective action taken in response to earlier protest is denied where agency reasonably determined that the proposals received in earlier acquisition... -
Inchcape Shipping Services Holding, Ltd., B-403399.3, B-403399.4, February 6, 2012
Posted on March 7, 2012 | No CommentsLink: GAO Decision Protestor: Inchcape Shipping Services Holding, Ltd. Agency: Department of the Navy Disposition: Protest Denied. _____________________________________________________________________________________________________ GAO Digest: Agency was not required to provide for the submission of revised proposals due to the fact that approximately one year had elapsed between the submission... -
Integrity Consulting Engineering and Security Solutions, LLC, B-405199.3, December 8, 2011
Posted on February 15, 2012 | No CommentsLink: GAO Decision Protestor: Integrity Consulting Engineering and Security Solutions, LLC Agency: Department of the Navy Disposition: Protest Denied. _______________________________________________________________________________________________________________ Digest: Protest alleging that the agency’s solicitation amendment, issued as part of corrective action in response to a protest by another firm, improperly disclosed proprietary... -
Northrop Grumman Technical Services, Inc., B-404636.11, June 15, 2011
Posted on July 13, 2011 | No CommentsLink: GAO Opinion Agency: Department of the Army Disposition: Protest denied. Keywords: Corrective Action General Counsel P.C. Highlight: Corrective Action following a prior protest must be reasonably related to the areas expressed by GAO as areas of concern, but will not necessarily require a reopening of... -
Iron Vine Security, LLC — Costs, B-403578.3, April 15, 2011
Posted on May 11, 2011 | No CommentsLink: GAO Opinion Agency: United States Agency for International Development Disposition: Request denied. Keywords: Corrective Action; Protest Costs; Clearly Meritorious Protest General Counsel P.C. Highlight: GAO may recommend reimbursement of protest costs, including reasonable attorneys’ fees, if GAO determines that the agency unduly delayed taking corrective action in the face...