It Is All in the Details: Offeror’s Proposal Must Exactly Follow the Requirements in the RFP

Created July 2014 In the matter of Veteran Technologists Corporation, Vet Tech argued that it was improperly excluded from consideration under the Department of Veteran Affairs request for proposals (RFP) for general management and business support services. Vet Tech was…

It Is All in the Details: Offeror’s Proposal Must Exactly Follow the Requirements in the RFP was last modified: January 23rd, 2015 by Rocky Galloway

ATR Logistic Company LLC, B-402606, June 15, 2010

Link: GAO Opinion Agency: Department of Army Disposition: Protest denied. Keywords: IFB; Bid compliance General Counsel P.C. Highlight: A bid must comply in all material respects with the IFB and should be filled out, executed, and submitted in accordance with the…

ATR Logistic Company LLC, B-402606, June 15, 2010 was last modified: June 24th, 2010 by General Counsel PC 703-556-0411